At the east end of East Capitol Street, the old RFK Stadium is gone. Hill Rag reported in September that the stadium had been taken down. The rest of the roughly 174-acre campus was still in planning and preconstruction. Listing copy on the Hill already describes homes as one block from Metro and "the coming Commanders District."
That phrase covers a lot. It includes a stadium, a rebuilt Metro station, a bus rapid transit line, thousands of parking spaces, up to 6,500 homes and a separate project on Reservation 13. Each one runs on its own clock, and only some have money behind them. Today's price on a Hill East rowhouse is a bet on those clocks. This fall's market gives buyers room to pay for the funded pieces and not much else.
November 2026: A Plan in Front of the Council
The District released the draft RFK Campus Master Plan on June 30 and closed public comment on August 14. The Office of Planning was then expected to revise it before sending it to the DC Council. The draft calls for 5,000 to 6,500 homes, at least 30 percent of them affordable, and six million to eight million square feet of mixed-use space across six districts. The Washington Commanders would lead the Stadium, Plaza and Riverfront districts. The District would oversee Kingman Park, the Recreation District and Anacostia Commons. A 65,000-seat enclosed stadium is still targeted to open in 2030.
Hill Rag put the plan's status plainly: "The plan is a framework, not a construction drawing." Revisions, Council review, Comprehensive Plan and zoning actions, environmental review and detailed engineering all come after it. The November Hill Rag describes the Council as still considering the Robert F. Kennedy Campus Master Plan Approval Resolution of 2026. That issue also reports that ANC 7D voted to send the Council a resolution backing a letter to the National Capital Planning Commission from Councilmembers Zachary Parker, Charles Allen and Wendell Felder. The letter raises concerns about the size of the G1 and G2 parking garages. It asks for street-level retail, construction below grade and smaller garages.
So the stadium date is set, but the land-use rules that will shape the blocks around it are still being written.
2027: The Year the Transit Gets Chosen and Priced
Two transit projects decide how much of the stadium crowd passes through Hill East on foot. They are on different footings.
The funded one is the Stadium-Armory station. According to Hill Rag's September report, the District and WMATA have agreed to fund design, plans are at 30 percent, and $300 million has been budgeted for station improvements. The need is large. A July Hill Rag analysis cited WMATA figures showing the station handles about 14,000 riders an hour today. In WMATA's high-use scenario, about 32,300 transit riders could leave within an hour after a game. Without upgrades, clearing that crowd could take more than two hours. With new elevators, escalators, stairs and an expanded north entrance, WMATA says it could take 60 to 90 minutes.
The other project has a schedule but no construction money yet. WMATA's Gold Line page, updated October 30, 2026, lists the bus rapid transit line along H Street NE and Benning Road NE as in concept planning. WMATA plans to pick a preferred concept in early 2027 and to identify final design and construction funding in spring 2027. In July, DDOT director Sharon Kershbaum told councilmembers the Union Station-to-RFK segment would cost an estimated $75 million. Hill Rag reported that no money had been set aside for it.
Location matters on this one. The transit center would sit on the RFK campus, and the proposed spot is 21st and C Streets NE. Residents have objected, and ANC 7D has suggested moving it to the south side of the campus. DDOT staff also said there would be no detailed traffic analysis until environmental review is complete, which is expected by summer 2027 at the latest. For a buyer, the line's route, station location and traffic effects stay open questions until 2027 decisions are made.
Hill East residents can see the plans in person at an open house hosted by Metro and DDOT. It is on Monday, November 30, 2026, at 6 p.m. at the Atlas Performing Arts Center.
2028 and the Years Before Kickoff
WMATA's schedule has Gold Line construction starting in summer 2028 and finishing in spring 2030. The station rebuild brings its own disruption. At a July 1 DC Council roundtable, Metro General Manager Randy Clarke said the work would require significant outages. Stadium-Armory sits on the tracks serving Largo and New Carrollton, and the work cannot happen during large events such as the Cherry Blossom Festival. Hill Rag wrote that "the region may feel the consequences of the stadium plan long before the first kickoff."
Most buyers think about game day. For someone who rides the Orange, Blue or Silver line from Stadium-Armory, the planned outages are the nearer change. Any home bought this winter will be owned during the construction years before it is owned in a finished district.
2030: Opening Day, With Game-Day Details Still to Come
The stadium and the Gold Line both aim for 2030, with bus service planned for summer 2030 to line up with the opening. WMATA's study estimates about 25,000 attendees arriving by car for a major event. District materials provide roughly 8,000 parking spaces at opening: about 6,000 in two garages and 2,000 in temporary surface lots on parcels meant for later development.
The draft sends most car traffic along four approaches:
- Southeast Boulevard from I-695 under Barney Circle
- Benning Road and the Whitney Young Memorial Bridge from the east
- Independence Avenue and C Street from the west
- A rebuilt Oklahoma Avenue NE with three to five reversible lanes before and after games
DDOT has described game-day tools such as traffic officers, temporary one-way streets and curbside controls, and it plans to work out those details closer to opening. A home on Independence Avenue SE or C Street sits on a named stadium approach today, and the game-day operating details for that street are set later.
2032: What's Scheduled for After Opening
Two pieces come after the stadium opens. The East Capitol pedestrian bridge over I-295 and CSX, which would help residents east of the river and near the highway reach the campus, is now expected in 2032 rather than 2030. A Gold Line extension east toward Benning Road could be built by 2032 if it hits targets like the first segment's. Both connections reach past Hill East, and both are scheduled for two years after the first game.
Reservation 13 Runs on Its Own Clock
Just south of the RFK campus, the 67-acre Hill East District has been planned since 2002. Its first phase produced the Park Kennedy apartments and The Ethel, and much of the site is still undeveloped. On July 14, the Council approved revised terms for R13 Community Partners to develop parcels C, E and H at 1900 Massachusetts Avenue SE. The plans call for townhouses, multifamily and mixed-use buildings, a hotel and a public park on Parcel E. Earlier materials described more than 1,200 homes, about 60,000 square feet of retail and a 150-room hotel.
The revised deal gives each parcel 32 months after construction starts, up from 30. The District, not the developer, now builds the Parcel E park and leases it to the developer for 25 years. A land disposition agreement, zoning review, financing, permits and final designs still come before construction. The 32-month window does not start until construction does. Those new homes and shops along Massachusetts Avenue SE are a longer-range prospect than the stadium.
What October Says About Who Has Time
The October 2026 Washington, DC market report from the Greater Capital Area Association of REALTORS covers the whole city, not Hill East alone. It shows a market where prices held while buyers gained room to negotiate. The citywide median sale price for October 2026 was $699,500, up 3.6 percent from October 2025. Sellers received an average of 94.8 percent of their original list price that month, compared with a five-year October average of 97.5 percent. October also had 6.2 months of supply, against a five-year October average of 4.0. Showings fell 11.8 percent from October 2025 to 8,642, and new purchase contracts dropped 15.2 percent to 512.
Prices that hold steady while supply builds and showings fall usually mean buyers have time and can push back on price. Near the RFK campus, that time is useful. The $300 million budgeted for the station rebuild is the most concrete commitment in the plan. The stadium has a 2030 target. The Gold Line's construction funding, the traffic plan and Reservation 13's start date are all still pending. A seller pricing for "the coming Commanders District" is pricing in all of it. In a city where October sales closed below original list on average, a buyer can ask the seller to justify each of those pieces.
FAQ
Has construction on the new stadium started? Hill Rag's September report said the old stadium had been taken down and the wider campus was still in planning and preconstruction. The November issue describes the master plan resolution as still before the DC Council.
Is the DC Armory part of the RFK plan? The Armory at 2001 East Capitol Street SE was not part of the federal transfer of the main RFK campus. In September, the National Park Service asked the National Capital Planning Commission to transfer administrative control of the roughly 9.4-acre site to the District, with the federal government keeping the land itself. The DC National Guard, headquartered at the Armory, is considering a move.
Where can I follow the Hill's other civic projects? Our Capitol Hill neighborhood page and our recent look at the Southeast Library reopening and the Rumsey closure cover projects closer to Eastern Market.
If you are weighing a home within walking distance of Stadium-Armory, bring the listing and your questions about the RFK timeline to The Lyndsi + Matt Team. Schedule a complimentary consultation.